Poland’s Key Environmental Decisions Take 660 Days on Average

Must read

Key environmental decisions in Poland take an average of 660 days to obtain, the daily Rzeczpospolita reported Thursday. It said the problem is a lack of money.

The newspaper notes that it takes the national roads agency GDDKiA an average of 662 days to obtain an environmental decision, and the rail infrastructure manager PKP PLK an average of 660 days. It also points out that Metro Warszawskie (Warsaw Metro) has been waiting four years, since July 15, 2022, for a decision on the city’s third metro line, and that Kraków’s airport authorities waited 10 years for a decision on building a new runway.

“The bottleneck is the Regional Directorates for Environmental Protection (RDOŚ), the provincial bodies that assess the environmental impact of investments,” the paper writes, citing the applications it analyzed.

The paper notes that Poland has 16 RDOŚ offices, each handling several thousand cases a year. By Rzeczpospolita’s estimate, that comes to at least 50,000 cases nationwide. Meanwhile, the paper reports, all the RDOŚ offices together employ a total of 1,309 people.

The Ministry of Climate and Environment’s answers to the paper’s questions show that the ministry sees a need to increase staffing and raise pay for key employees. However, the ministry indicated that any increase in staffing depends on securing adequate funds in the state budget.

According to Rzeczpospolita, an interim solution is expected to be regulations now being prepared that would tie the amount of the stamp duty to the actual workload of officials. But the paper points out that the reform proposal “has been stuck at the consultation stage for several months.” (PAP)